Abstract


This research was conducted to analyze the causes of potential risks during construction projects at CV. Tirto Kencana. The study was conducted using the Failure Mode Effect and Analysis (FMEA) method. FMEA method is a commonly used method in identifying and analyzing potential risk factors in order to solve problems. After conducting the analysis, it was found that the potential risks that occurred were caused by negligence in making the agreement document during the procurement or tender stage process and negligence at the work implementation stage. The root of the problem is the problem when making the work agreement document and the problem of natural factors that occur when the technical work takes place.


Keywords


risk management; development projects; risk matrix; FMEA; 5 whys

Full Text:

PDF

References


Flanagan, R., and Norman, G. Risk Management and Construction. Cambridge University Press, London, 1993.

Chapman, C., and Ward, S. Project Risk Management. Processes, Techniques and Insights. Second Edition. John Wiley & Sons Ltd, West Sussex NJ, 2003.

Cheng, M., and Lu, Y. Developing a risk assessment method for complex. Automation in Construction, 58, 2015, pp. 48-59.

Liu, Y., Kong, Z., and Zhang, Q. Failure modes and effects analysis (FMEA) for the security of the supply chain system of the gas station in China.

Ecotoxicology and Environmental Safety, 164, 2018, pp. 325-330.

Villarini, M... Cesarotti, V., Alfonsi, L., and Introna, V. Optimization of photovoltaic maintenance plan by means of a FMEA approach based on real data. Energy Conversion. and Management, 152, 2017, pp. 1-12.