PEMODELAN PENJADWALAN LINIER DENGAN ALOKASI SUMBER DAYA MANUSIA PADA PROYEK PERUMAHAN

Hedwig Angdiarto Tan(1*), Ratna S. Alifen(2),


(1) Mahasiswa Pascasarjana Magister Teknik Sipil UK Petra
(2) Dosen Pascasarjana Magister Teknik Sipil UK Petra
(*) Corresponding Author

Abstract


ABSTRACT: Linear scheduling method is suitable for projects with repetitive activities, as well as tipical mass product units such as a road, apartment, and residential housings. In this research linear schedule modeling was carried out on residential typical housings project of 50 units. The simulation of linear scheduling is to minimize the idle times by using time buffers and human resources allocation so that the usage of human resources can be as efficient as possible.

The research findings show that the 8th simulation by using buffers has a project duration of 314 days were chosen with 18 working groups, compares to 9th simulation without buffers that has a duration of 180 days and 134 days of idle time which with 1522 man day of inefficient.


Keywords


housing, scheduling linear, human resources simulation.

Full Text:

PDF

References


Kass, P.E., and Leong, M.W. (2008). "Linear Schedules for Tunnel Projects." Jacobs Associates. Seattle, WA.