Penerapan Metode Resource Loaded Scheduling Untuk Aplikasi Manajemen Proyek Pada Perusahaan Kontraktor “X”

David Filigon Lie(1*), Alexander Setiawan(2), Lily Puspa Dewi(3),


(1) Program Studi Informatika
(2) Program Studi Informatika
(3) Program Studi Informatika
(*) Corresponding Author

Abstract


Currently PT. Liberty Persada Sakti still uses CPM method when making schedule, because CPM does not factor in resources the result is not that accurate for estimating time period of a project. And all records of transactions done and calculation of RAB still done manually in papers and microsoft excel, that causes the company became susceptible for mistake made in calculating finance.

Looking at the background of the problem, an appliaction is designed to help PT. Liberty Persada Sakti. The application will use Resouce Loaded Scheduling method for making schedule for a project, recording company finance and controlling project management. Application will uses PHP programming language and MySQL for making database.

The results obtained from this thesis is that, the new system is helping the company to create and record RAB, and by comparing the calculated result from CPM and Resource Loaded Scheduling, both method have it’s own advantages and disadvantages.

Keywords


Resource Loaded Scheduling; Project Management; Critical Path Method; Budget Estimate Plan

Full Text:

PDF

References


“A Guide to the Project Management Body of Knowledge Seventh Edition”. Project Management Institute. 2017.

Abdou, Saed M., Yong Kuan., Othman, Mohammed. 2016. Project Complexity Influence on Project Management Performance – The Malaysian Perspective. MATEC Web of Conferences. 66: 00065.

Belch, Geroge E., & Belch, Michael A. 2004. Advertising and Promotion : An Integrated Marketing Communications Perspective, Sixth Edition. McGraw-Hill, Inc. Bab 7.

Feitelson, Dror G. 2015. Workload Modeling for Computer Systems Performance Evaluation. Cambridge University Press. Section 8.4 (page 422).

Griffith, A. F. 2006. Scheduling Practices and Project Success. Cost Engineering, 48(9), 24-30.

Matthews, M. D. 1994. Resource Scheduling: Incorporating Capacity Into Schedule Construction. Project Management Journal, 25(2), 44–54.

Mesly, Oliver. 2017. Project Feasibility – Tools for uncovering points of vulnerability. New York, NY: Taylor and Francis, CRC Press. 546.

Piryonesi, S.M., Nasseri, M., & Ramezani, A. 2018. Resource Leveling in Construction Projects With Activity Splitting and Resource Constraint : A Simulated Annealing Optimization. Canadian Journal of Civil Engineering, 46 (999), 81-86.